Data Collection:
A very comprehensive data collection was
performed at construction sites. Took assistance from the site supervisor to
compute data as precise as possible. We
used to go to the site at least 3 times in a week for a period of 4 months.
Since we had our classes as well on the week days, so we taught the site
supervisor to help us measure data in the hours we weren’t available. Being
undergrad students we had 6-7 hours available for project on daily basis
(except for the project day). Since site work is minimum of 8 hours, which at
times exceeds to 10-11 hours (overtime work) and we could only manage 6-7
hours, so the extra hours measurements were taken by the site supervisor on our
behalf, and later we counter checked those measurements using our own activity
analysis. We remained vigilant while collecting data.
The scope of our project includes four
tangible factors, hence the data we acquired touched all four aspects. For the
first factor, ‘level of experience of
labour’ we looked for sites that had labours with various years of working
experience in the specified activities. On construction site there were labours
with a ranging work experience i.e. from a few months to years of experience.
To bring uniformity and reliability in our results, we categorized experience
into parts i.e. 0-5 years, 5-10 years, 10-15 years etc and cases like labour
having experience of 23 years or 30 years were very rare, hence we ignored
those cases.
‘Complexity of a project’
was
our second aspect. To cover this aspect we chose two sites with ‘higher
complexity’ and two sites with lower complexity. To define a project as
complex, we had to go through literature review. The construction process is
always made up of a multitude of interacting parts. Therefore, in simple terms,
this may suggest that construction is generally complex in nature. However, the
dictionary definition adds another interesting property, i.e. `being difficult
to understand or carry out, intricate, involved’. Since not all construction
production processes satisfy this property, it may then be acceptable to
consider it as a meaningful cut-off point that makes a distinction between a
`complex’ construction process and a simple or `non-complex’ one.
Many experts and researchers have defined a complex process in quite a
number of specific ways. Perrow (1965) defined the complexity of a task
as the degree of difficulty of the
search process in performing the task, the amount of thinking time required to solve work-related problems and the body
of knowledge that may provide guidelines for performing the task. Thompson
(1981) considered complexity as the measure of the difficulty of coordinating a production process comprising of
activities that lack uniformity of work.
Malzio et al. (1988) suggested that a complex process is that
which comprises of operations that are innovative
and conducted in an uncertain situation.
Experts consider project complexity in a number of ways. They see a complex project as follows.
1. That having a large number of different systems that need to be put
together and/or that with a
large number of interfaces between elements.
2. When a project involves construction work on a confined site with
access difficulty and requiring
many trades to work in close proximity and at the same time.
3. That with a great deal of intricacy which is difficult to specify
clearly how to achieve a desired goal or how long it would take.
4. That which requires a lot of details about how it should be executed.
5. That which requires efficient coordinating, control and monitoring
from start to finish.
6. That which requires a logical link because a complex project usually
encounters a series of revisions during construction and without
interrelationships between activities it becomes very difficult to successfully
update the programme in the most effective manner.
Keeping in mind all these points, we rated
our four site projects on a complexity scale. For which we used the method of
Likert scale (on a scale of 1 to 5). 1 representing fulfilment of the condition
at a very small extent & 5 representing fulfilment of the condition at a
very high extent. Sites were rated by observing the site and interviewing the
staff.
Fig 3.6 Complexity of a project
Or even cost wise, Gulberg mall is most
costly project, site is least in terms
of cost of project, as well.
Our third factor is ‘temperature’, literature review says that studies on ‘temperature effect on productivity are not
consistent’. We used to note
hourly data of temperature whenever we were working at site. We took data
during winters therefore there weren’t many fluctuations in the temperature.
‘Overtime’
is our fourth factor. Overtime in this research is defined as the hours worked
beyond the typical 40 h scheduled per week or 8 hours of work per week days.
Extended overtime is frequently used to:
·
Meet tight
project targets from owners
·
Make up for
late changes and project delays
·
Attract
skilled labour to a project
Some owners and contractors consider
extended overtime as necessary and required to meet the demands for faster
schedules or to staff their projects. For them, extended overtime is the norm,
their standard approach to projects.
In our case, the numbers of hours
exceeding 8 hours work in a day, is equal to the number of overtime hours. In
our sites, it ranged from 1 hr to 5 hrs.
3.4 Process of acquiring data on field with respect to its factors:
3.4.1 Tangible:
Steps:
1.
Reach site,
and see what activities are being performed.
2.
Start
noting data of those activities on the designed site performa, at one hour
intervals.
3.
If you
reach the site late or leaves a bit early, take the assistance of foreman or
site supervisor to fill the remaining hours data. In order to make sure that
data of whole day at construction site is noted in the performa.
4.
Labour
skill level: It was measured by taking readings of labour with a particular
experience. For e.g. one day, work done by labour having experience of 0-5
years, working on a particular activity (let’s say concreting), was measured.
And on another day, work done by labour having experience of 5-10 years,
working on the similar activity (concreting), was measured. Same goes for
labour having experience 10-15 years.
5.
Overtime:
Work done in the hours after 8 working hours was noted as overtime work.
6.
Temperature:
Since we were taking readings at intervals of 1 hour, hence we noted
temperature for 1 hour intervals
7.
Complexity:
Since we rated each project on a complexity scale, so the productivity data for
each site was calculated in hourly average format.
3.4.2 Intangible:
Steps:
1.
Developed a
project management process performa
2.
Interviewing
construction site staff and observing management system
3.
Verifying
our performa results with readings obtained from site
Following is the sample of project management process performa
Project Management Process Performa 1.
Site name: 2.
Competency & Number of foreman (years of
experience): 3.
Documentations: 4.
Company SOPs: 5.
Safety Management: 6.
Company SOPs communicated to the administrative body
(till foreman level): 7.
Tools, Techniques & Policies regarding quality
management: 8.
Number of complete projects: |
Fig 3.7 Project management process
performa
No comments:
Post a Comment