3RD Topic
Methodology Of Productivity
Research methodology is descriptive, observation and
interviews. After a comprehensive literature review, we divided our methodology
into two components: tangible and intangible.
In first phase, we made a questionnaire which
consisted of intangible factors from management and material category.
Conducted a pilot survey by distributing the questionnaire to more than 30
civil engineering experts. Using relative importance index, shortlisted one
factor from each category.
3.2 Intangible factors & their relative importance
indices (RII):
Factors RII
Management category:
Supervision ,performance, monitoring ,and control
0.89
Competencies of the project manager 0.9
Loss in productivity I caused if room chang either
orders 0.72
Lackioficapabilityioficontractor’sisitei
management to organization-site works 0.83
Adequacy of planning and risk management
process 0.76
Adequacy of method of construction 0.76
Project management style 0.75
Lack of coordination among the construction
parties 0.84
Relationship management degree of harmony,
trust, and cooperation 0.74
Materials & Tools category:
Lack of tool and equipment in the market 0.75
Suitability or adequacy of the plant and
equipment used 0.81
Adequacy of technology used 0.77
Late supply of construction materials 0.89
Material shortage at project site 0.94
Table 3.0 Intangible factors & their RII
3.2.1 Shortlisted intangible factors:
In second phase, we performed a preliminary survey in
twin cities (Rawalpindi-Islamabad) to select construction sites. Construction
sites we chose were:
1. Gulberg
mall
2. Pakistan
Housing Authority Apartments
Construction sites were chosen by keeping in mind, the
ease of access, cooperation from the construction company staff, distance from
our residency etc.
Following four activities are selected to evaluate the
construction labour productivity with its factors:
1. Brickwork
2. Steel
installation
3. Concreting
4. Shuttering/formwork.
Our project is focused on labour productivity so we considered only those activities which are labour intensive and the main variable in the productivity is human. One can find many such activities going on in any construction site, but we made sure that the selected 4 activities were common in all our sites
• Brickwork
Brickwork is one of the major activity, usually used
as a non-bearing material. At some place block masonry is also used instead of
brickwork, but in Pakistan brickwork is found more often at construction sites.
It is labour intensive activity which is performed by masons and helpers. We
measured it in ‘no of bricks’ being placed in a ‘unit hour’.
Fig 3.1
• Steel installation
steel bar or
mesh of steel wires installed as a tension device in reinforced concrete and
reinforced masonry structures to strengthen and aid the concrete under tension.
Anywhere where steel is being placed, whether in slab or column, it’s
considered in rebar installation. It is labour intensive activity which is
performed by steel fixers and helpers. We measured it in ‘tons/hr’
Fig 3.2 steel installationSteel installation
• Concreting
is one of the most frequent activity on site. It’s a
major process in construction and is also easy to measure. This labour
intensive activity is measured in m3/hr.
Fig 3.3 concreting
• Shuttering
and Formwork
Shuttering and Formwork is quite a technical task to
carry out. Arrangement of shuttering needs to be accurate to ensure that
concrete attains proper strength in right orientation. This labour intensive
task is measured in ‘sft/hr’.
Measurements of productivity
Before going to the field to measure physical factors,
a standard form was developed which was used throughout the field work to take
measurements from the site work. Since our project involves measuring four
activities in relation to four different physical factors, therefore we made
sure that the form we devise is kept as generic as possible. It included
details like, activity name, site name, site supervisor, time (on hourly
basis), work done, number of labours, date, observer, labour experience, labour
details, observation number, temperature and productivity in (unit/hr/labour).
Following is our designed form:
I really liked your review. With your permission, I would like to share it on my social media accounts. I will cite the source. Thank you.
ReplyDelete