How to check work at site in civil engineering Concrete, Slab and Beams, Excavation, Formwork of all structure members
When the excavation work on site Checklist for civil site-engineer in construction work on site.
1. Is that
safety the safety norms being covered as per HSEM process.
2. Excavation plan prepared and approved by client/
consultant is that ok for excavation.
3.Check for completion of other activity such as a
contour survey discus with consultant and client.
4. All size and layout alignment and size of
excavation marked on ground as per excavation plan and checked by consultant
surveyor.
5.There any underground utilities like sewer line
water line cable inform about site incharge and take action then start work of
excavation.
6.The all markings done and approved by Consultant
surveyor as per drawing.
7. Check for dewatering arrangements like peter engine
dewatering pump mud pump pipe arrangement.
8.If blasting work like stone and hard rock check if
the explosive carried in specify boxes with safety.
9. Check that all instrument is ok.
10.Check the all machinery part is that ok for work
don according to safety.
Excavation work |
Formwork checklist for engineer supervisor and site inspector.
Checklist for contractor civil site-engineer in construction work on site.
1. Check the all
the safety norms being covered as per HSEM process.
2.all the plate/plywood cleaned and polished properly.
3. Oil or polish use of the surface cleaning of Shattering.
4.Vertical member shear wall columns lift wall check
the starter is okay.
5.Check alignment of all verticals members
at floor level with respect grid line.
6.Check plumb of vertical members 2 sides.
7. Check the support all side of shuttering is that ok.
8. Check the concrete cover block cover is per drawing.
Formwork |
How to Check Slab and beams at site.
1.Check the alignment of beams size sides according to
drawings proper done as per size given in drawing.
2. Check the line and label of slab.
3.Check the size of slab grid to grid according
dimension to drawings.
4.Check the form work is water proof not hole show in
formwork.
5.Check the vertical support for vertical members like
columns lift wall retaining wall etc .
6.Check the selling of gape hole in slab is proper
block with tape or other material.
7.Proper cleaning for next use.
8.Check horizontal support are OK for beams or slab.
9 Check out the cleaning of all Shuttering is ok.
10 Check the all size beams columns slab according to drawing is okay.
Form work of slab and beams |
How to Check reinforcement at site.
Some Checklist for civil site-engineer in construction work on site.
1. Bar bending schedule approved use for cutting
bending and fixing.
2.Check the cutting bending the bar as per approved
BBS.
3.Check Bar dia Shape of bar dimension of bar.
Number of bar as per drawing.
4.Check cleanliness of bar straight bar.
5. Check is that okay spacing of steel as per drawing.
6. Check steel fixing as per steel drawing and
approved BBS.
7.Check for satisfactory tying with bending wire steel
bar is proper.
8. Overlap length and location of length as per giving
section in drawing.
9. Check concrete cover is ok.
10.Check the master ring above columns at the slab
level for vertical dowels.
11.Check the steel aliment on placing method for main
or distribution bar.
12.proper chair bar for bottom and top steel mesh for
cover.
Steel work |
When the concreting pouring at site following Check list during concrete.
How to check for civil site-engineer in construction work on site.
1.Check the slump is it ok as per given mix design and
then ok
2.Check temperature of concrete in case of temperature
controlled concrete then allow to concrete.
3. Check placing method of concrete is it right is per
specification given by client.
4.Proper vibrator being concreting done for good and
smooth surface.
5. Check the provision of construction joint material as
per drawing.
6.Check the surface of slab level is done by surveyor
and as per giving drawing plan.
7.Check the top finishing of slab all slab finishing
is good.
8.Check the top level and surface of slab.
Concreting |
No comments:
Post a Comment